Verde Two Construction Update August 2018

We are pleased to share the construction progress on site. By the end of August 2018, we have completed façade window works. While Aluminum Composite Panel installation is targeted to be completed by October 2018. Waterproofing is 90% in progress, as we are progressing work on level 21 above.

Service elevators are in operations, and passenger elevators will be installed by September 2018. Swimming pool facilities and hardscape works are in progress. In the interior, marble installation is progressing to level 29.